Statement of a problem № m1419

        next    

Consider the Western Hills Shopping Center Project summarized by Figure 13.6 and Table 13.2. Suppose the project has been underway for seven weeks. Activities A and E have been completed. Activity F has commenced but has three weeks remaining. Activities C and D have not started yet. Activity B has one week remaining (it was not started until week 2). Update the activity schedule for the project. In particular, how has the slack for each activity changed?